Norway Suspends Grid Capacity Reservations for Large Power Projects Such as Data Centers

Written by

in

Norwegian transmission operator Statnett has suspended accepting new grid capacity reservations and some technical approval applications until August 1, 2027, at the latest. Statnett is studying the response and power consumption change requirements of large computing facilities during grid disturbances. The data centers currently being tracked have a combined capacity of 32.1 GW, of which 800 MW is already connected to the grid. The Norwegian government has also proposed a permit system for existing and future data centers, but it has not yet been legislated, and the main principles are expected to be determined in autumn 2027.